Rehab Estimating for Flips (Room-by-Room)

Room-by-room costs, the line items rookies miss, and how to phase a rehab budget so you do not run out of money at drywall.

Repairs are the number you control and the number you will be wrong about. Estimate by scope, not by feel, and carry contingency like it is a line item — because it is.

Fast per-square-foot bands

Scope levelTypical costWhat it includes
Cosmetic$18–$28 / sq ftPaint, flooring, fixtures, light kitchen/bath refresh
Standard$30–$45 / sq ftFull kitchen + baths, some mechanicals, minor layout work
Heavy$50–$80 / sq ftAll mechanicals, roof, windows, framing repairs, layout changes
Gut$85–$130+ / sq ftDown to studs, new systems, possible structural work

Big-ticket line items

ItemRange
Architectural roof (1,500 sq ft footprint)$9,000–$16,000
Furnace + central AC$8,000–$14,000
200A electrical service + rewire$7,000–$18,000
Full repipe (PEX)$5,000–$11,000
Windows (per unit, installed)$550–$950
Kitchen (mid-grade, 10x12)$12,000–$22,000
Full bath$7,000–$14,000
Foundation crack repair / drainage$3,000–$25,000+
Add 10–15% contingency

On any property built before 1978 in the Northeast, budget contingency plus lead-safe practices and possible knob-and-tube or asbestos abatement. These are not surprises; they are statistics.

The line items people forget

Phase the budget

  1. 1Phase 1 — make it dry and safe: roof, water intrusion, structure, demo.
  2. 2Phase 2 — systems: electrical, plumbing, HVAC, then inspections before you close walls.
  3. 3Phase 3 — finishes: drywall, paint, flooring, kitchen, baths.
  4. 4Phase 4 — curb appeal and punch list, in the two weeks before photos.

Get two written bids per trade on anything over $5,000, and never pay more than 30% up front. Draw schedules tied to completed phases keep everyone honest.